Climbing process: Check all climbing organizations, frames, and obstacles → Install electric hoists and debug pre-tightening → Remove the upper frame from structural connection → Remove the safety net on the outside of the frame at the broken section → Raise the frame by 100mm → Remove the unloading seat → Raise the frame by one floor height → Install the unloading seat → Connect the upper climbing frame (connection spacing not greater than 6m) → Close the safety net on the outside of the frame at the broken section → Transfer the lifting steel wire rope to the upper device position → Remove the lowest anti-falling rod and install it to the topmost position → Construct one floor of the structure → Install the upper adjustable tie rod and wall-attached guide seat → Check before lifting → Prepare for the next lifting cycle.