1, the construction load (personnel, materials and machinery weight) used on each 1m?shelf surface of the operational layer shall not exceed the following prescribed values or construction design values; the standard value of construction load (weight of personnel, apparatus and materials on the operational layer), structural scaffolding to take 3kN/m2, decoration scaffolding to take 2kN/m?
2, mortar and container total weight shall not be greater than 1.5kN; construction equipment single weight shall not be greater than 1kN, the use of manpower on the rack handling and installation of the self-weight of the components shall not be greater than 2.5kN. structure construction when the number of construction steps of the operation shall not exceed two layers, each layer of the operational load shall not be greater than 3KN / m? Scaffolding construction load must be strictly controlled during decoration construction, while the number of construction steps shall not exceed three layers, and the operating load per layer shall not be greater than 2KN/m?
3, the material set on the shelf surface should be placed neatly and firmly, does not affect the construction operation and the passage of personnel.
4, the maximum operating height of the operator on the rack should be normal operation, forbidden to add padding or a single scaffold plate on the rack to increase the operating height.
5, in the operation, prohibit the arbitrary removal of the basic scaffolding frame bars, integral bars, connecting fasteners, safety nets and connecting wall pieces. Indeed, the operation requires temporary removal, must be agreed by the competent person, take the corresponding temporary reinforcement measures, and after the completion of the operation, to be restored in a timely manner.
2, mortar and container total weight shall not be greater than 1.5kN; construction equipment single weight shall not be greater than 1kN, the use of manpower on the rack handling and installation of the self-weight of the components shall not be greater than 2.5kN. structure construction when the number of construction steps of the operation shall not exceed two layers, each layer of the operational load shall not be greater than 3KN / m? Scaffolding construction load must be strictly controlled during decoration construction, while the number of construction steps shall not exceed three layers, and the operating load per layer shall not be greater than 2KN/m?
3, the material set on the shelf surface should be placed neatly and firmly, does not affect the construction operation and the passage of personnel.
4, the maximum operating height of the operator on the rack should be normal operation, forbidden to add padding or a single scaffold plate on the rack to increase the operating height.
5, in the operation, prohibit the arbitrary removal of the basic scaffolding frame bars, integral bars, connecting fasteners, safety nets and connecting wall pieces. Indeed, the operation requires temporary removal, must be agreed by the competent person, take the corresponding temporary reinforcement measures, and after the completion of the operation, to be restored in a timely manner.