How does the climbing and landing of the climbing frame work?
Date:
2019-09-06 17:44
Climbing process: all check the climbing organization, frame and obstacles → install electric hoist and debug pre-tightening → dispense with the upper frame and structure pulling connection → dispense with the safety net on the outside of the frame at the broken piece → raise the frame 100mm → remove the unloading seat → raise the frame one floor high → install the unloading seat → pulling connection to the upper climbing frame (the distance between pulling connections is not more than 6m) → close the safety net on the outside of the frame at the broken piece → raise the Wire rope turnover to the upper installation position → remove the lowermost anti-fall bar, installation to the uppermost position → construction construction layer → installation of the upper adjustable tie rod, attached wall guide seat → check before raising → ready to enter the next lifting cycle.